The reconstruction of Cockburn Street is progressing on schedule thanks to the efforts of the staff at Campbell’s Trucking. Below is the tentative schedule for the coming weeks

Week of August 19th

Complete the installation of Sanitary Sewer and Water Mains

Continue the installation of Storm Sewer and resident’s individual water and sewer services

Week of August 26th

Complete the installation of Storm Sewer Network

Installation of resident’s Water and Sewer Services to property lines

Week of September 2nd

Construction of retaining wall

  • Road excavation and granular placement for new roadbed

Residents are responsible for covering the cost of replacing their water and sewer services from their property line to their homes. The Town encourages residents to reach out to a plumber/contractor of their choice for a quotation to complete these works. If residents choose to have their private services replaced, a building permit will be required. For building permit information please call 613-267-3311 ext.2222

Staff appreciate your patience and understanding on this construction project to date. Residents can continue to contact Noah Greer, Manager of Construction & Development Services, for further updates and questions as they arrive at:

Sincerely,

Grant Machan, C.E.T.

Director of Environmental Services

80 Gore Street East

Perth, Ontario K7H 1H9

Phone: 613-267-3311 ext. 2233

Email: gmachan@perth.ca